Location:
Tremont, Pennsylvania
Client:
Design/Build Contractor
WDP performed
an extensive geotechnical investigation for this 1.8 million square foot
distribution facility constructed within and above previous deep-mined
and strip-mined coal fields. The investigation (deep test borings and rock
coring) provided design recommendations for foundation and floor slabs,
below-grade walls, pavements, and site preparation/structural fill placement
including strip-mine backfill remediation, deep-mine collapse potential
and hard rock excavation/blasting. WDP provided full-time construction
inspection and materials testing for all strip-mine remediation and structural
fill placement operations (approx. 1 million CY), foundation examinations
and slab subgrade preparations, concrete placement (approx. 35,000 CY),
structural steel and masonry, and paving operations (approx. 28 acres).

Due to WDP's
involvement:
-
Strip-mine backfills
were remediated affording conventional shallow foundations.
-
Deep-mine collapse
assessment minimized development risks.
-
Bedrock profiling
identified hard rock excavation areas and blasting requirements.
-
On-site crushing
plant permitted strategic fill material blending and placement, thus allowing
all on-site materials to be used without off-site borrow.
-
Considerable concrete
mix design testing using both flexural beams and test cylinders as well
as washed concrete gradations to confirm unreinforced slab design criteria
batched using on-site concrete batching facility.
|
|
Location:
Allentown, Pennsylvania
Client:
Design/Build Contractor
WDP performed an extensive geotechnical and geophysical
investigation for this 500,000 square foot distribution/storage facility
due to erratic limestone bedrock depths and potential sinkhole/solution
cavity activity. The investigation provided design recommendations for
foundation and floor slabs, below-grade walls, pavements, and site preparation/fill
placement including lime stabilization. The geophysical survey provided
limestone bedrock surface profiles and rippability characteristics (seismic
refraction) as well as sinkhole/subsurface void detection (electrical resistivity).
WDP provided full-time construction inspection and materials testing for
all structural fill placement operations, foundation examinations and slab
subgrade preparations, concrete placement, structural steel and masonry,
and paving operations.

Due to WDP's involvement:
-
Wet, clayey soils necessitated lime stabilization, thus permitting
sitework to proceed in winter months and increasing overall soil bearing
strengths.
-
Limestone bedrock profiling identified hard rock excavation
areas and virtually eliminated sinkhole/subsurface void development.
-
Strategic fill material blending and placement allowed all
on-site materials to be used without off-site borrow.
-
Considerable concrete mix design testing using both flexural
beams and test cylinders as well as washed concrete gradations to confirm
unreinforced slab design criteria.
|